RateBuild 2: Building a unit rate

Part 2 of the RateBuild series. Build a construction unit rate from scratch: labour, equipment and materials line by line, with formula pricing and wastage, using floor tiling at $143.76 per square metre as the worked example. Everything shown can also be done by asking the Map Metra connector in Claude or ChatGPT.

How to

  1. 1

    Opening the rate breakdown

    Double-click the code to open its rate breakdown. The Rate tab shows the result, and it is locked, because it is worked out from the lines on the Resources tab.

  2. 2

    Labour

    Choose Add item. Each line has a type, a name, a quantity, a unit and a price.

  3. 3

    Working alongside

    Add a labourer the same way, at fifty dollars an hour. Then tick Alongside.

  4. 4

    Equipment

    Change the type to Equipment for plant and tools. Here, a wet saw for cutting the tiles runs for the same zero point six seven hours, at three dollars twenty five an hour.

  5. 5

    Materials and formulas

    Materials work the same way. Tiles come in boxes, so type the price as a sum, starting with an equals sign.

  6. 6

    Adhesive and grout

    Add the adhesive at five and a half kilograms per square metre, priced from a twenty kilogram bag at twenty eight dollars. Then the grout, at zero point four four kilograms, from a five kilogram bag at thirty dollars.

  7. 7

    The Rate tab

    Back on the Rate tab, the lines are summed into a labour rate, a material rate and an equipment rate. Together, they make the combined rate of one hundred and forty three dollars seventy six per square metre.

  8. 8

    Saving the rate

    Choose Save. In the library, the code now shows its labour, its material and equipment, and its rate, and the Unpriced label has gone.